About the Operational Council for the project "Implementation of an integrated information system SAP S / 4 HANA"

News EN Hits: 823

Project manager Elena Gutseva from the integrator company IT Professional Solutions presented a work plan for the next stage.

From 09.11.2021 until 19.11.2021, the system will be tested with the participation of specialists from Fergana Oil Refinery Plant LLC and specialists from the integrator company IT Professional Solutions LLC.

Preliminary tests of CIS based on SAP S / 4 HANA will include the following areas:

Accounting and tax accounting

Purchasing and inventory management

Sales management

Treasury management

Maintaining regulatory and reference information

Equipment maintenance and repair management

Investment management

Production accounting

Management accounting

Prior to the start of preliminary testing, the testing team reviewed the test scripts and user instructions. When passing the test scenarios, comments from key users of the Fergana Oil Refinery Plant will be recorded, then the Integrator's project team will draw up a schedule for eliminating these comments, all revised comments will be tested by key users of the plant on their own in the SAP S / 4 HANA test system.

As a result of the meeting, it was decided to consider stage 3.3 "Implementation" completed in full, and to start work on stage 3.4 "Deployment".

 

Press Service of “Fergana Oil Refinery Plant” LLC

 